B.C. to go ahead with Site C dam, with new $16B budget and delayed to 2025

Reviews recommend more oversight, beefed up foundation stability work

Premier John Horgan says his government will continue building the Site C mega dam in northeastern B.C., with an increased budget of $16 billion and a one year delay.

Last August, the government commissioned a special review after BC Hydro acknowledged a serious concern about the dam’s foundational stability. Those reports were made public Friday (Feb. 26), with the province accepting all recommendations.

Special advisor Peter Milburn recommended additional oversight, but did not find evidence of mismanagement.

The government calculated it would cost $10 billion to terminate the dam, and that it will be preferable to complete Site C at the higher price than to absorb the loss. Horgan said cancelling the dam would have an immediate impact to ratepayers of an estimated 26 per cent rate increase over 10 years.

About $6 billion has already been spent, and construction on the dam is over half complete, BC Hydro said.

The Peace River has been diverted, the coffer dams are done and two of the massive turbines have arrived from Brazil. Energy Minister Bruce Ralston also said most of the environmental impacts have already occurred.

In reaction to the announcement, Green Party leader Sonia Furstenau criticized the decision, saying “this isn’t the last time [British Columbians] are going to hear about costs going up.” The Green Party have consistently opposed the dam.

The BC Liberals, who initially approved the dam under former premier Gordon Campbell, have not released an official statement. Interim leader Shirley Bond did re-tweet a comment from pundit Shane Mills saying the NDP “have completely bungled oversight of project of project that was on-time and on-budget.”

RELATED: BC Liberal critic blasts ‘lack of transparency’ on Site C

When the Liberals left power it 2017, they said the project was on time and on budget, but when the BC Utilities Commission reviewed the project later that year, they called that claim into question, predicting probable cost overruns and delays.

The Union of B.C. Indian Chiefs has also consistently opposed the dam on the grounds that the First Nations in the area were not adequately consulted and did not give their consent – impact benefit agreements notwithstanding – despite the province’s voice interest in reconciliation.

Kukpi7 Judy Wilson, UBCIC Secretary-Treasurer, added that the UN Committee on the Elimination of Racial Discrimination has called on Canada to suspend Site C until it has the free, prior and informed consent of Indigenous Peoples.

RELATED: Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

As for geotechnical concerns, engineers virtually evaluated the small movement shifts that had been observed and recommended solutions to shore up the strength of the foundation. These necessary changes plus COVID-19 adjustments make up about half of the increases costs, while the remaining $2.6 billion is set for other unrelated cost overruns.

The actual rate increase from completing the project are unknown, as they will not take effect until the dam is complete – now estimated for 2025. BC Hydro has estimated a roughly $36 annual increase for an average rate payer.

RELATED: First Nation calls for release of Site C report in open letter to premier

The dam has been controversial since the 1980s when it was first proposed as a series of dams on the Peace River. Supporters say the mega dam will supply B.C. with stable energy to meet growing capacity needs.

Those opposed group under a variety of reasons, a primary critique being the ballooning budget.

Site C was originally approved with an $8.8 billion budget in 2014. It increased to $10.7 billion after the BC Utilities Commission reviewed the project in 2017 when the NDP took over government.

Concerns around dam stability have been raised by the public for years. Other complaints are about the ecological impact, First Nations rights in the area, and whether B.C. really needs the power supply.

Do you have something to add to this story or something else we should report on? Email: zoe.ducklow@blackpress.ca


BCHydroenergy sector

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

B.C. Finance Minister Selina Robinson outlines the province’s three-year budget in Victoria, April 20, 2021. (B.C. government video)
B.C. deficit to grow by $19 billion for COVID-19 recovery spending

Pandemic-year deficit $5 billion lower than forecast

A syringe is loaded with COVID-19 vaccine at a vaccination clinic run by Vancouver Coastal Health, in Richmond, B.C., Saturday, April 10, 2021. THE CANADIAN PRESS/Jonathan Hayward
67 new cases of COVID-19 in Interior Health

Thirty people in the region are hospitalized with the virus, 11 of whom are intensive care

An animal carrier full of bullet holes and containing a dead animal was found near Castlegar. Photo: Colleen Schwartz
Castlegar woman finds dead animal inside carrier riddled with bullet holes

The remains were discovered near Syringa Creek Provincial Park

People are shown at a COVID-19 vaccination site in Montreal, Sunday, April 18, 2021, as the COVID-19 pandemic continues in Canada and around the world. THE CANADIAN PRESS/Graham Hughes
211 new COVID-19 cases in Interior Health over the weekend

Currently, there are 875 active cases of the virus in the region

A nurse prepares a dose of the COVID-19 vaccine in Kelowna on Tuesday, March 16. As of April 19, more than 230,000 doses have been administered across the Interior Health region. (Phil McLachlan/Black Press)
More than 230K doses of COVID-19 vaccine administered across Interior Health

A total of 220,216 first doses and 13,775 second doses have been given to residents across the B.C. Interior

Four homes in Johnson Flats were at serious risk of falling into a neighbourhood section of the Kettle River, according to capital project manager Justin Dinsdale. Photo: Laurie Tritschler
Grand Forks shields riverside homes against erosion

Crews have built a modified dike along a section of the Kettle River in Johnson Flats

A man pauses at a coffin after carrying it during a memorial march to remember victims of overdose deaths in Vancouver. THE CANADIAN PRESS/Darryl Dyck
B.C. announces historic half-billion-dollar funding for overdose crisis, mental health

Of it, $152 million will be used to address the opioid crisis and see the creation of 195 new substance use treatment beds

Children’s backpacks and shoes are seen at a CEFA (Core Education and Fine Arts) Early Learning daycare franchise, in Langley, B.C., on Tuesday May 29, 2018. THE CANADIAN PRESS/Darryl Dyck
B.C. budget to expand $10-a-day child care, but misses the mark on ‘truly universal’ system

$111 million will be used to fund 3,750 new $10-a-day spaces though 75 additional ChildCareBC universal prototype sites over the next three years.

The IIO is investigating after a police dog bit a man during a traffic stop near Ladysmith on April 17, 2021. (Black Press Media stock photo)
Man arrested in incident at Canada-U.S. border near Roosville

A man who crossed the border illegally was apprehended by U.S. officials

Mak Parhar speaks at an anti-mask rally outside the Vancouver Art Gallery on Sunday, Nov. 1, 2020. Parhar was arrested on Nov. 2 and charged with allegedly violating the Quarantine Act after returning from a Flat Earth conference held in Geenville, South Carolina on Oct. 24. (Flat Earth Focker/YouTube.com screenshot)
Judge tosses lawsuit of B.C. COVID-denier who broke quarantine after Flat Earth conference

Mak Parhar accused gov, police of trespass, malfeasance, extortion, terrorism, kidnapping and fraud

Ambulance paramedic in full protective gear works outside Lion’s Gate Hospital, March 23, 2020. Hospitals are seeing record numbers of COVID-19 patients more than a year into the pandemic. (The Canadian Press)
B.C.’s COVID-19 infection rate declines, 849 cases Tuesday

Up to 456 people now in hospital, 148 in intensive care

Christy Clark, who was premier from 2011 to 2017, is the first of several present and past politicians to appear this month before the Cullen Commission, which is investigating the causes and impact of B.C.’s money-laundering problem over the past decade. (Darryl Dyck/Canadian Press)
Christy Clark says she first learned of money-laundering spike in 2015

The former B.C. premier testified Tuesday she was concerned the problem was ‘apparently at an all-time high’

Most Read