Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Slocan Valley to be ‘lit up’ with high-speed internet in 12 months

125 kilometres of fibre-optic cable to be laid from Nakusp to Playmor Junction

RED resort announces new ski lift

Topping lift will add new ski area to resort, reduce bottleneck on Motherload chair

Paramedics union raises alarm over spike in out-of-service ambulances

Staffing shortages affecting service levels in Kootenays

Kim Johnson retires from rec department

Johnson had worked at Grand Forks Recreation Department for 25 years

COLUMN: 2018 second-largest on record for food bank

Boundary Community Food Bank added 109 new clients last year

VIDEO: The ‘most cosmopolitan’ of butterflies could migrate to B.C.

The painted lady butterfly will likely arrive this summer from Southern California

Is it a homicide? B.C. woman dies in hospital, seven months after being shot

Stepfather think Chilliwack case should now be a homicide, but IHIT has not confirmed anything

Indecent caller handed 18-month conditional sentence

Vancouver Island man pleaded guilty to making indecent phone and video calls to women across B.C.

Sources say Trudeau rejected Wilson-Raybould’s conservative pick for high court

Wilson-Raybould said Monday “there was no conflict between the PM and myself”

First Nations public art piece stolen in Nanaimo

Spindle Whorl went missing over the weekend, according to Nanaimo RCMP

Father-son duo at B.C. Children’s Hospital helps new dads fight depression

The pair teamed up to introduce the only known research-based mindfulness workshop for new dads

Mexican restaurant in B.C. told to take down Mexican flag

General manager of Primo’s Mexican Grill in White Rock: ‘I’ve never heard of anything like this’

B.C. NDP moves to provide tax credits, tax cut for LNG Canada

Provincial sales tax break of $596 million repayable after construction

COLUMN: Smart phone too powerful a tool to yank from students’ hands

Rather than ban them from schools, let’s teach kids to harness their phone’s power and use it properly

Most Read