B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Columbia River Treaty to be renegotiated in early 2018

News came in a Tweet from the U.S. Department of State

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

Castlegar Rebels take flight in win over Grand Forks

Team speed was too much for the visiting Grand Forks Border Bruins to handle.

Property crime on the rise in Grand Forks: RCMP

Grand Forks RCMP sat down with the Gazette to talk property crime and community solutions.

RDKB elects Russell as board chair

Grace McGregor will be vice-chair of the board.

VIDEO: New series takes in-depth look at sexual harassment in B.C.

Black Press takes a hard look at sexual harassment in B.C.

B.C. polygamous leader argues charge should be dropped in charter challenge

Winston Blackmore argues some of the evidence shouldn’t be used against him

LETTER: Proportional representation makes votes count

Fair Vote Canada representative responds to Tom Fletcher column

B.C. dog owners warn about chain collars after puppy almost strangled

Young Rottweiler pup couldn’t breathe after another dog caught tooth on his collar

Accused NYC subway bomber expected to face federal charges

Akayed Ullah, 27, was charged Tuesday with terrorism and weapons related charges

Strategy announced for Indigenous cancer care

Various stakeholders have come together to provide a road map from prevention to survivorship

Environmental groups slam NDP decision to continue with Site C

Construction industry, meanwhile, is cautiously optimistic about how the project will look

B.C. Conservatives applaud Site C decision

B.C. Conservatives happy with government decision to proceed

Hwy. 1 avalanche improvements promise less delays

B.C.’s new remote avalanche-control systems near Revelstoke are ready for avalanche season

Most Read